Skip to content
Independent certification guide · exam data reviewed November 2026 Study guidesBrowse by fieldHow we review
Find a certification

PMP - Project Management Professional

PMP - Project Management Professional practice questions

30 free questions with explanations across 3 exam domains. Pick an answer to see if you got it right.

These are original practice questions based on the official exam outline, not real exam questions.
Page 2 of 3Score: 0 / 0
Question 11 of 30Business Environment
A project has a fixed deadline that cannot move, but scope is negotiable. When new requirements are proposed mid-project, the project manager should:
Answer: B. With a fixed constraint (time), the triple constraint model requires trading off the flexible variables (scope) — this is core Business Environment reasoning about constraint management.
Question 12 of 30Process
What is the PRIMARY difference between a risk and an issue in project management?
Answer: B. This distinction is foundational: risks are proactively managed uncertain future events, while issues are current problems requiring immediate resolution.
Question 13 of 30Process
A project team uses velocity from previous sprints to forecast how much work can be completed in upcoming sprints. This technique is called:
Answer: B. Using historical velocity to forecast future capacity is a core agile empirical process control technique, distinct from predictive EVM or critical path methods.
Question 14 of 30People
During a retrospective, a team member says nothing negative even though the sprint clearly had problems. As facilitator, the project manager should:
Answer: B. Psychological safety is central to effective retrospectives; when people are silent despite obvious problems, the facilitator's job is to create conditions where honest input feels safe.
Question 15 of 30Process
A project charter is BEST described as a document that:
Answer: B. The charter's specific purpose is formal authorization and granting PM authority — it is a high-level authorizing document, not a detailed planning artifact like a WBS or risk register.
Question 16 of 30People
Which of the following is the MOST effective way to build trust on a newly formed cross-functional team?
Answer: B. Team chartering is a specifically recommended technique in the People domain for establishing shared working agreements early, accelerating trust-building rather than leaving it to chance.
Question 17 of 30Process
A stakeholder consistently provides vague, conflicting feedback on requirements. The BEST approach to resolve this is:
Answer: B. Structured elicitation techniques exist specifically to convert vague stakeholder input into clear, testable requirements — this is a core Process domain skill.
Question 18 of 30Business Environment
What distinguishes a program from a project?
Answer: B. This is the standard PMI definition — coordinated management of related projects to realize benefits unavailable through individual management is the defining characteristic of a program.
Question 19 of 30Process
A project manager notices scope creep occurring gradually without formal change requests. The ROOT CAUSE is most likely:
Answer: B. Scope creep specifically results from the absence of a firm baseline and enforced change control.
Question 20 of 30People
Which conflict resolution technique involves both parties giving up something to reach a mutually acceptable solution?
Answer: B. Compromising is specifically defined as a lose-lose/win-win technique where both sides concede something.

About these practice questions

Are these real PMP - Project Management Professional exam questions?

No. They are original practice questions written to test the topics in the official exam outline. Real exam questions are confidential, and sites claiming to have them break the vendor's rules.

How should I use these PMP - Project Management Professional practice questions?

Answer each one before reading the explanation, note the topics you get wrong, and go back to those parts of your study plan.